Overview
qTest Manager is highly configurable, whether you plan to use qTest on its own, or with JIRA, Rally, or VersionOne. Follow the steps within the appropriate Quick Start Guide below to quickly set up and use qTest Manager.
qTest Manager Core Quick Start Guide
Follow these steps to set up qTest Manager and begin using it without any integration to JIRA, Rally, or VersionOne:
Initial Setup
Using qTest Manager
- Create a Test Plan
- Create requirements in qTest Manager or import requirements from Excel
- Add requirements to the Test Plan
- Create a test case or import test cases from Excel
- Link requirements to test cases
- Plan your tests in Test Execution as follows.
- Execute the test run
- Submit the defects you find during Test Execution
JIRA Quick Start Guide
Follow these steps to set up qTest Manager and begin using it with JIRA:
Initial Setup
Using qTest Manager with JIRA
- Create a test case or import test cases from Excel
- Link requirements to test cases
- Plan your tests in Test Execution as follows.
- Execute the test run
- Submit the defects you find during Test Execution
Rally Quick Start Guide
Follow these steps to set up qTest Manager and begin using it with Rally:
Initial Setup
Using qTest Manager with Rally
- Create a test case or import test cases from Excel
- Link requirements to test cases
- Plan your tests in Test Execution as follows.
- Execute the test run
- Submit the defects you find during Test Execution
VersionOne Quick Start Guide
Follow these steps to set up qTest Manager and begin using it with VersionOne:
Initial Setup
Using qTest Manager with VersionOne
- Create a test case or import test cases from Excel
- Link requirements to test cases
- Plan your tests in Test Execution as follows.
- Execute the test run
- Submit the defects you find during Test Execution